If you need to activate many objects at the same time, this is possible with the report RADMASG0_C3. A use case would be, for example, if there were problems with the support package import and the objects were not activated.
There are three options to use that report to activate objects:
- Specify transport(s) (a support package is also a transport) which contain(s) the objects to be activated
- Specify objects directly
- List objects in external table
You can run the report both in dialog and in the background as a background job by creating a variant and scheduling the report with the variant as a background job.
You have to look at the different possible parameters that can be set; which ones you need depend on your individual application. There are too many options to be able to suggest a “standard”.